Huilong: 2000 t/a Chlorantraniliprole project is expected to be put into operation by the end of 2024
Recently, some investors asked Anhui Huilong’s Chlorantraniliprole project production time and capacity in the investor interactive platform:
Q: When is it expected to put into production the Chlorantraniliprole technical under construction? Is 2000 t/ar a near-term goal?
A: The company's 2000 tons Chlorantraniliprole project is expected to be put into operation by the end of 2024, but the new product needs a certain climbing period to stable mass production. Please pay attention to the specific production data in the periodic report.
According to the previous project environmental assessment and groundbreaking information, the annual output of 2,000 tons of Chlorantraniliprole and intermediates project is located in Anhui Bengbu fine chemical high-tech industrial base; The total investment of the project is 943.2 million yuan, of which 15.5 million yuan is invested in environmental protection, accounting for 1.61% of the total investment. The project covers an area of about 235 mu, divided into two phases of construction, after reaching the annual output of 2000 tons of Chlorantraniliprole technical and intermediates.
Looking for chemical products? Let suppliers reach out to you!
2026-06-16
-
ECHEMI-Intermediate for Pesticide 2024
The magazine will be published in Jan 2024 and distributed at the ICSCE 2024 in Dubai, UAE. CAC 2024 in Shanghai ,China .And online for permanent download.Published in: Feb.2024
Agrochemical News
-
Potassium Chloride Weekly Report (May 18, 2026 - May 24, 2026)
2026-05-25 -
Urea Weekly Report (May 18, 2026 - May 24, 2026)
2026-05-25 -
Complex Fertilizer Weekly Report (May 18, 2026 - May 24, 2026)
2026-05-25 -
Potassium Chloride Weekly Report (May 11, 2026 - May 17, 2026)
2026-05-18 -
Urea Weekly Report (May 11, 2026 - May 17, 2026)
2026-05-18